BUILDING A VILLAGE

CONSTRUCTION TIMELINE

  • July 2018 to February 2019: Kier refurbish Block B.
  • February 2019: Block B is finished. We all move from Block A to Block B.
  • February to August 2019: Kier refurbish a few extra rooms in Block A and demolish the 1960s part of Block A.
  • 22 August 2019: Blocks A and B are finished.
  • August to late September 2019: Kier finalise the landscaping of our external spaces.

 

 